if three persons can do a piece of work in 4 days then 4 person can do it in how many days
Answers
Answered by
14
Answer:
3 days
Step-by-step explanation:
if 3 persons are doing the work in 4 days
then, 1 person will do the same work in 12 days
so 4 persons will do the work faster
∴ 12/4
=3 days
Answered by
4
Answer:
3 days
Step-by-step explanation:
it is a inverse variation
so,A/q
3×4=4x
12/4=x
3=x
so, 4 persons can do the same piece of work in 3 days