if twelve machines working 7 hrs a day can finish a work in 18 days in how many days will 16 machine working 9 hrs a day finish twice the work?
Answers
Answered by
0
21 days
Solution:-
let number of days be x.
machines hours days quantity
(↓). (↓). (↑). (↑)
12. 7. 18. 1
16. 9. x. 2
____________________________
x/18 = (12/16)×(7/9)×(2/1)
x = (12×7×2×18) / (16×9×1)
x = 21 days
Answer
hope this helps you