If two persons 'A' and 'B' require 35 days to complete a task.Person 'A' completes the same task in 60 days. How many days will be required by person 'B' to complete the task.
Answers
Time taken by (A + B) to complete the task = 35days.
Then work done by (A + B) in 1 day = 1/35.
Now, Time taken by A to complete the work = 60days.
Then work done by A in one day = 1/60.
Therefore time taken by B to complete the work = (1/35 - 1/60) = 12 - 7 / 420 = 5/420 = 1/84.
Therefore total time taken by B to complete the work = 1÷ 1/60 = 1 × 84 days = 84days.
Answer:
.Person 'B' completes the same task in 84 days.
Step-by-step explanation:
.Person 'A' completes the same task in 60 days.
.Person 'B' completes the same task in D days.
.Person 'A' and B complete the same task in 35 days.
NOW
one day work done by A =1/60
one day work done by B =1/D
one day work done by A =1/35
so
1/60 +1/D = 1/35
1/D = 1/35 - 1/60
= 12/420 -7/420
= 5/420
1/D =1/84
D =84