Math, asked by hemantmehta28051, 10 months ago

If workers can build a wall in 18 hours how many workers will be required to do the same work in 30 hours

Answers

Answered by amitnrw
0

60 %  of initial Workers required

Step-by-step explanation:

Question is not complete

Let assume if M workers can build a wall in 18 hours

then how many workers will be required to do the same work in 30 hours

=> M Worker can build wall in 18 hours

=> Total number of Man hrs required = 18 M  Man hrs

Total Man hrs Required = 18 M

Work to be completed in 30 hrs

=> number of Workers required = 18M/30

= 3M/5

3M/5 Workers required

= 60 %  of initial Workers

if Questions has initially 5 Workers then 3 Workers required

if Questions has initially 10 Workers then 6  Workers required

if Questions has initially 15 Workers then 9  Workers required

Learn more:

10 men can prepare 20 toys in 3 days working 12 hours a day. In how

https://brainly.in/question/7505586

12 person working 6 hours daily can build a bridge in 30 days .if 15 ...

https://brainly.in/question/13388256

24 men working 8 hours a day finish work in 10 days how many men ...

https://brainly.in/question/7520445

Similar questions