if x+1 men will do the work in x+1 days find the number of days that x+2 men can finish the same work
Answers
Answered by
101
We know that,
x+1 men = x+1 days
1 man= (x+1)*(x+1) days
x+2 men= (x+1)²/x+2 days
Therefore, x+2 men can do the same work in (x+1)²/x+2 days
x+1 men = x+1 days
1 man= (x+1)*(x+1) days
x+2 men= (x+1)²/x+2 days
Therefore, x+2 men can do the same work in (x+1)²/x+2 days
Answered by
25
(x + 2) men can finish the same work is
days.
Step-by-step explanation:
We have,
(x + 1) men will do the work = (x + 1) days
To find the number of days that (x + 2) men can finish the same work = ?
∴ 1 man will do the work = days = 1 days
Then, (x + 2) men will do the work = days
(x + 2) men will do the work days
Hence, (x + 2) men can finish the same work is days.
Similar questions