if x+1 men will do the work in x+1 days find the number of days that x+2 men can finish the same work
Answers
Answered by
2
Step-by-step explanation:
Given:-
x+1 men will do the work in x+1 days.
To find:-
find the number of days that x+2 men can finish the same work ?
Solution:-
Given that
X+1 men will do the work in X+1 days
Number of men = X+1
Number of days to complete the work = X+1
We know that
Number of men increases then Number of days decreases
So men and days in the indirect Proportion.
=> M×D = Constant
Let the number of days to complete the same work by (X+2) men be Y days
We have ,
We know that
M1 D1 = M2 D2
M1 = X+1
D1 = X+1
M2 = X+2
D2 = Y
On Substituting the values on the above formula
=> (X+1)×(X+1) = (X+2)×Y
=> (X+1)^2 = (X+2) ×Y
=> (X+2)×Y = (X+1)^2
=>Y = (X+1)^2 / (X+2) days
or
Y = [(X2+2X+1)/(X+2)] days
Answer:-
(X+2) men will complet the same work in
(X+1)^2 / (X+2) days or [(X2+2X+1)/(X+2)] days
Used formulae:-
- Number of men increases then Number of days decreases ,So men and days in the indirect Proportion. M×D = Constant
- M1 D1 = M2 D2
Similar questions