if X can finish a job in 4 hours and Y can finish the same job in 8 hours independently, then they together will finish the job in
Answers
Answered by
2
Answer:
2.6 hr
Step-by-step explanation:
in one hour x can do a job=1/4
in one hr y can do job= 1/8
both together do this job in
1/(1/4+1/8)
1/(3/8)
8/3 hr
2.6 hr
both will do this work in 2.6 hour