If x can finish a job in 4 hours and y can finish the same job in 8 hours, then
they both together will finish the job in
(A) 160 minutes
(B) 150 minutes
(C) 140 minutes
(D) 120 minutes
(E) None of these
Answers
Answer:
Given :-
Number of hours taken by X to finish a job = 4 hours
Number of hours taken by Y to finish a job = 8 hours
Conversion (From hours to minutes as the answer is expected in minutes) :
∴ 1 hour = 60 minutes.
∴ 4 hours = 60 × 4
= 240 minutes
∴ 8 hours = 60 × 8
= 480 minutes
To find :-
The time they both can finish the job in = ?
Solution :-
Time taken by X to finish a job = 4 hours
Time taken by Y to finish a job = 8 hours
∴ ( x + y )'s one day's work = 1/4 + 1/8
= 3/8
∴ Required time = 8/3 hours
= (8/3 × 60) minutes
= 160 minutes
∴ X and Y together will do the job in 160 minutes.
Correct option :- (A) 160 minutes.
___________________________________
Answer:
160 minutes
Step-by-step explanation:
8/3 ×60 =160