If Yash works alone he would take 4 days more to complete the job than if both Yash and Kush worked
together. If Kush works alone, he would take 9 days more to complete the job than they work together.
How many days would they take to complete the work if both of them worked together?
Answers
It would take them 6 days to complete the work together.
Given:
If Yash works alone he would take 4 days more to complete the job than if both Yash and Kush worked together. If Kush works alone, he would take 9 days more to complete the job than they work together.
To Find:
How many days would they take to complete the work if both of them worked together?
Solution:
Let Yash and Kush together complete the work in x days.
Therefore, Time taken by Yash = (x+4) days
Time taken by Kush= (x+9) days
+ =
=
Therefore, it would take them 6 days to complete the work together.
The number of days would they take to complete the work if both of them worked together is 36 days.
Given:
Yash works alone he would take 4 days more to complete the job than if both Yash and Kush worked together. If Kush works alone, he would take 9 days more to complete the job than if they worked together.
To Find:
The number of days would they take to complete the work if both of them worked together.
Solution:
To find the number of days would they take to complete the work if both of them worked together we will follow the following steps:
As given in the question:
Let the Yash and kush take x days to complete the work together.
Now,
As given in the question:
Time taken by the Yash in working alone is 4 times more than working together.
So,
Time is taken by Yash in working alone = x + 4
Also,
Time is taken by kush in working alone = x + 9
Now,
Forming the equation we get,
2x² - x² = 36
x² = 36
Henceforth, the number of days would they take to complete the work if both of them worked together is 36 days.
#SPJ2