(ii) 2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days.Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.

Answers

Answered by tnwramit1
2
This is ur ans hope it will help you in case of any doubt comment below
Attachments:

chiragsaxena7: thank bro
tnwramit1: np
Answered by Ankitajha212
1

Answer:

Number of days taken by a woman = 18 days

Number of days taken by a man = 36 days

Step-by-step explanation: