iii) Rachit took the contract to complete the work in 360 days but he has 120 workers
who can complete the work in 420 days. How many more men should he hire to finish
his contract?a 20
b)40
c) 140
d) 60​

Answers

Answered by urvashiraina
1

40 is your answer....