Illustration 8: A factory working for 50 hours a week employs 100 workers on a job work. The
standard rate is Re. 1 an hour and standard output is 200 units per gang hour. During a week in June
ten employees were paid at 80 p. an hour and five at Re. 1.20 an hour. Rest of the employees were
paid at the standard rate. Actual number of units produced was 10,200. Calculate labour cost
variances.
Answers
Answer:
Accessing a particular part of Data is possible easily only in
Answer:
150 (F)
Explanation:
(i) Cost Variance = Standard Cost – Actual Cost
5,100 – `4,950 = `150 (F)
Workings:
(a) Calculation of Actual Cost:
85 workers for 50 hours @ 1 per hour = 4,250
10 workers for 50 hours @ 80 p. per hour = 400
5 workers for 50 hours @ `1.20 per hour = 300
Total actual cost 4,950
(b) Calculation of Standard Rate:
Standard cost per (gang hour) = 100 × 50 × `1 = `5000
Standard production (per gang hour)
= 100 × 200 × 50 = 10000 unit
Standard rate per unit = `5000
10000
= 50 p. per unit.
(c) Calculation of Standard Cost:
Actual production × Standard rate 10,200 units × 50 p. per unit = `5,100
(ii) Rate Variance:
As the actual wage rate has deviated from the standard in respect of only 15 workers out of a total of 100 workers, wages rate variance would be calculated only in respect of these 15 workers.
Actual Hours (Standard Rate – Actual Rate)
Therefore, 500 Hours (`1 – 80 p.) = `100 (F)
250 Hours (`1 – `1.20) = `50 (A)
Thus, the total rate variance is `50 (F).
(iii) Efficiency Variance: Efficiency variance is indicated by the fact that, as compared with standard production of 10,000 units (200 units × 50 hours), the actual production is 10,200 units
Standard Rate (Standards Hours – Actual Hours) `1 (5,100 - 5,000) = `100 favourable. Calculation of Standard Hours= 5000 10200 = 5,100 hours.
10000
Yield Variance:
Standard labour cost per unit of output (SY – AY)
0.50 (10,000 – 10,200) = `100 (F)
Verification: Cost Variance = Rate Variance + Efficiency Variance
150 (F) = 50 (F) + `100 (F)