In 10 days A can do ½ of a job and b can do ⅓ of the job. In what time will they do ⅙ of the job working together?

Please explain. ​

Answers

Answered by nmansingh632
1

5/6

Step-by-step explanation:

if 1 worker works in = 1/2

second worker works in = 1/3

together = 1/2+1/3=5/6