Math, asked by singhudit874, 1 month ago

In 75% of the time that B takes to do a piece of work, A does half the work. Together they take 18 days to complete the work. C alone can complete the same work in 24 days. All the three started the work together but B left 5 days before the completion of the work. In how many days was the whole work completed?​

Answers

Answered by sushmitha9116
0

Answer:

30 days

Step-by-step explanation:

Let B takes x days to do the work.

According to the question

A takes 2×

4

3x

=

2

3x

(A+B)s 1 days work=

18

1

then

x

1

+

3x

2

=

18

1

3x

5

=

18

1

x=

3

18×5

=30

Hence B takes 30 days to do work

Answered by dikshaagarwal4442
0

Answer:

The whole work was completed in 28 days.

Step-by-step explanation:

Let's assume time taken by A, B, and be a, b, and c, respectively.

From the problem, we know that:

In 75% of the time it takes for B to do the work, A does half the work.

(3/4)B × (1/2)A = 1 (1 represents the whole work)

Simplifying the equation, we get:

A = (8/3)b

Together, A, B, and C take 18 days to complete the work.

1/a + 1/b + 1/c = 1/18

Work done by C alone in 24 days.

c = 1/24

Let's substitute the value of A in terms of B into the equation we got for A and B working together:

1/a + 1/b + 1/c = 1/18

1/[(8/3)b] + 1/b + 24 = 1/18

Simplifying the equation, we get:

b = 36/7

Now we can find the value of A:

A = (8/3) * (36/7) = 96/7

So, the combined rate of A and B working together is:

1/a + 1/b = 7/96

Now let's consider the scenario where A, B, and C start working together but B leaves 5 days before the completion of the work.

Let's assume that the whole work is completed in d days. This means that B worked for (d-5) days and A and C worked for d days.

Let's use the combined rate formula again, but this time we'll use (d-5) for the time B worked:

1/a + 1/b = 7/96

1/a + 1/b + 1/c = 1/18

1/a + 1/c = 1/((d-5)/b)

Substituting the values we know, we get:

1/(96/7) + 1/(36/7) = 7/96

1/(96/7) + 1/(36/7) + 1/24 = 1/18

1/(96/7) + 1/24 = 1/((d-5)/(36/7))

Simplifying the equations, we get:

d = 28

Therefore, the whole work was completed in 28 days.

To know more about work concept, click on the link below:

https://brainly.in/question/15114333

To know more about rate formula, click on the link below:

https://brainly.in/question/49353677

#SPJ2

Similar questions