in a company 25 workers can compete a work in 12 days in how many days will 50 workers
Answers
Answered by
0
Answer:
Number of workers= 25.
Number of days taken to complete the job= 12 days.
To find:
Number of days to complete job if number of workers =50
=25*12/50
=6 days