In a company, it takes 4 employees 4 days to complete a task. It would take 2 employees 8 days to complete the same task. Which function can be used to represent e, the number of employees working on the task, and d, the number of days it takes them to complete that task? direct variation; d = ke direct variation; de = k inverse variation; d = ke inverse variation; de = k

Answers

Answered by amitnrw
4

Given : it takes 4 employees 4 days to complete a task. It would take 2 employees 8 days to complete the same task

To Find : Which function can be used to represent e, the number of employees working on the task, and d, the number of days it takes them to complete that task

direct variation; d = ke

direct variation; de = k

inverse variation; d = ke

inverse variation; de = k

Solution:

4 employees 4 days to complete a task

=  4 e * 4 d

= 16ed

2 employees 8 days to complete a task

=  2 e * 8 d

= 16ed

16ed =  16ed

=> d  = 16/e

if number of employees increases days decreases

if  number of employees decreases days increases

Inversely vary

correct option

inverse variation;  de = k

Learn More:

The variable X is inversely proportional to Y if x increases by P ...

https://brainly.in/question/8648255

Which of the following quantities are inversely proportional? The ...

https://brainly.in/question/25739436

Answered by kaylianascott10
1

Answer: inverse variation; d=ke

Step-by-step explanation:

edge2020 pre test

Similar questions