In a factory 150 workers where ingage to finish a pice of work in a surtain number of day how where if 4 are every day accept the first day it will take 8 more day to finished the work find the number of day in which work was to be complited
PeshwaBajirao:
bhai chapter khula kab tha ki close kar de
Answers
Answered by
3
Answer:
Step-by-step explanation:
let the work be complete in x days
The work should have been complete by x-8 days.
Total man-days= 150(x-8)
As four worker drop on each day
The total work days are 150,150-4, 150-8..... 150-(x-1)4
These are in arithmetic progression where
a1=150 d= - 4 and n=x
so total working man-days= x(2a1-4(x-1))/2
= x(300-4x+4)/2
Then we have 150(x-8)=x(304-4x)/2
- 300x-2400= 304x-4x²
- 75x-600=76x-x²
- x² -x -600=0
- (x-25)(x+24)=0
solving we have x=25
The work was complete in 25 days.