In a project, a team of 400 labourers were
assumed to complete a job in 18 months. Later
on, it was required to complete the job in
10 months. The number of extra labourers are
employed to complete the work is
(1) 340
(2) 420
(3) 320
(4) 720​

Answers

Answered by ayush12345616
0

Answer:

this answer is 320 bro kk bro

Answered by sonibarnwal7654
2

Answer:

720 labour

Step-by-step explanation:

labour required to complete the process in 18 months-400

labour required to complete the process in 1 month =400×18=7200

no of labour required to complete the process in 1 0 months=7200÷10

=720 labourers ANS