Math, asked by anirudhchhatwa4872, 11 months ago

In an army camp there were provision for 250 men for 40 days if another 150 men join in the camp how long will the provisions last?

Answers

Answered by 1234amartyanjan
11

Answer:

25

Step-by-step explanat

answer in attachment

Attachments:
Answered by akashsonam8423
5

Answer:

250 men provision the work 40days

1 men provision same work =250×40=10000

if another 150 men join the group ,the total no. of men =250+150=400

thus , 400 men finished the work =

10000/400

=25 days