in aproject effort estimation is performed by whom

Answers

Answered by sakeenabanu112
0

Answer:

Identify the sequence of activities that need to be performed for the project to be completed. Divide activities into tasks that can be measured. Estimate the effort (in person hours/days) required to complete each task. Combine effort estimates of tasks of activity to produce an estimate for the activity.

:-)