In department X the following data are submitted for the week end in
February 21,
Standard output for 40 hours per week
1400 units
Standard fixed overhead
Rs. 1400
Actual output
1200 units
Actual hours worked
32 hours
Actual fixed overhead
Rs. 1500
Calculate variance from standard.​

Answers

Answered by soham1qw3e
0

Answer:

176 answer is this ...............