In how many days of working 8 hours each day, can 12 men do the same work as 10 men working
9 hours a day do in 16 days?
Answers
Answered by
0
Answer:
Below is Your Answer
Step-by-step explanation:
the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days
=working 8 hours per day.
=12*8*x =10*16*9
We will get the value of x = 15.
=> So they will need 15 days to complete the same amount of work.
Answered by
1
Answer:
15 days
Step-by-step explanation:
amount of work = number of days × hours they work × number of men's
=> number of days × 8 × 12 = 16 × 9 × 10
=> number of days = (16×9×10) ÷ (8×12)
=> number of days = 15