In how many days of working 8 hours each day, can 12 men do the same work as 10 men working 9 hours a day do in 16 days
Answers
Answered by
0
Answer:
12*8*x = 10*16*9You will get the value of x = 15. So they will need 15 days to complete the same amount of work.
Answered by
1
Answer:
they will need 15 days to complete the same amount of work.
Assume that the number of days required be x.
Now, the work done by 10 men in 16 days working 9 hours per day would be equal to the work done by 12 men in x days working 8 hours per day.
12*8*x =10*16*9
Solve the equation to get the value of X.
Hope u like it