Math, asked by amit278173, 1 year ago

In how many days of working 8 hours each day , can 12 men do the same worj as 10 men working 9 hours a days do in 16days

Answers

Answered by TooFree
3

Answer:

15 days


Step-by-step explanation:

Find the workload:

Workload = 10 men x 9 hours x 16 days

Workload = 1440 man-day-hour


Find the number of days 12 needed if they work 8 hours a day:

Number of days = 1440 ÷ (12 x 8)

Number of days = 15


Answer: The 12 men will need 15 days.


TooFree: Thank you for the brainliest :)
Answered by stark17A
1
find the work load of peoples
16×9×10 = 1440 hour mens work
find the number of days 12 needed if they work8 hours per day;
no. of days =12×8/1440
15 days

amit278173: thax
stark17A: yeah thanks too