In ms-excel which functions will calculate the number of workdays between 6/9/2013 and 8/12/2013

Answers

Answered by aaradhyagupta43
4

Explanation:

To calculate the number of workdays between two dates, you can use the NETWORKDAYS function. NETWORKDAYS automatically excludes weekends, and it can optionally exclude a custom list of holidays as well. Note that NETWORKDAYS includes both the start and end dates in the calculation if they are workdays.