English, asked by mokshadaj05, 6 months ago

In Network Diagram, Three Time values are
assigned for each activity for calculating
average time are:​

Answers

Answered by ArmishSaifi
0

Answer:

Sorry I can't under stand this question

Explanation:

Sorry

Answered by bsharma23sl
0

Answer:

The time values assigned to each activity for the calculation of average time in a network diagram are Optimistic time (to), Most likely time (tm), and Pessimistic time (tp).

Explanation:

  1. Optimistic time - This time value is required for calculating the average time when there are no complications and hurdles.
  2. Most likely time - In this time, the activity is most likely to be completed. This time estimate makes allowance for some unforeseen delays by considering normal circumstances.
  3. Pessimistic time - This time value is required in unforeseen difficulties and unusual complications.

#SPJ3