in order to complete a work in 28 days 60 mens are required how many men will be required ifthe same work has to be completed in 40 days?
Answers
Answered by
0
Answer:
please give Alok if you have id is Dhyey1012W
I will follow you
Answered by
1
Let there are 28×60 parts of that work = 1680 parts
in 40 days, men needed = (total work)/days = 1680/40 = 42 men
Method 2
work is always the same, so
men1×days1 = men2×days2
⇒28×60= men2×40
⇒men2 = 42