Math, asked by singjind09, 1 year ago

In order to complete a work in28 days ,60 men are required. How many men will be required if the same work is to be completed in 40 days?.​

Answers

Answered by mahajananmol222
0

Answer:312

Step-by-step explanation:1 men=60^28=1680

40 men =1680÷40=312

Answered by Anonymous
0

Given,

In order to complete a work in 28 days, 60 men are required.

To find out,

How many men will be required if the same work is to be completed in 40 days?

Explanation:

As it is given, 60 men are required to complete a work in 28 days.

That means, 60 men can complete a work in 28 days.

How many men can complete the same work in 40 days?

Solution:

Let the number of men required to finish work in 40 days be 'x'.

60 men __________ 28 days

x men ____________ 40 days

Now, it is inversely proportional.

Inversely Proportional: when one value decreases at the same rate that the other increases.

As it is inversely proportional,

28 × 60 = 40 × X

1680 = 40 × X

1680/40 = X

X = 42

Therefore 42 men are required to finish the work in 40 days.

Similar questions