Math, asked by lartika279, 11 months ago

In the beginning, Ram works at a rate such that he can finish a piece of work in 24 hrs, but he only works at this rate for 16 hrs. After that, he works at a rate such that he can do the whole work in 18 hrs. If Ram is to finish this work at a stretch, how many hours will he take to finish this work?​

Answers

Answered by sabnamkhan29
2

Explanation:Ram’s 16 hr work = 16/24 = 2/3. Remaining work = 1 – 2/3 = 1/3.

Using work and time formula: This will be completed in 1/3 × 18 i.e. 6 hrs.

So, total time taken to complete work = 16 + 6= 22 hrs.

Answered by Anonymous
4

Answer:

hiiii

your answer is here !

Step-by-step explanation:

Ram’s 16 hr work = 16/24 = 2/3.

Remaining work = 1 – 2/3 = 1/3.

Using work and time formula:

This will be completed in 1/3 × 18 i.e. 6 hrs.

So,

=> total time taken to complete work = 16 + 6= 22 hrs.

follow me !

Similar questions