Business Studies, asked by avahazarika7242, 1 year ago

In which phase of pdca you can confirm whether the solution has met the desired goal?

Answers

Answered by farwa8
5

PDCA- Plan, Do, Check, Act is the business process management model that helps to solve the problems and run the processes smoothly.

In the third step i.e. Check, proposed solution is implemented on a pilot project/small scale and evaluated whether the issue has been resolved or desired result has been achieved.  

If desired results are achieved, solution is implemented on whole process and if negative results are achieved, the process is repeated from step 1.  


Answered by aqibkincsem
3

PDCA cycle stands for Plan Do Check Act cycle. It is also called as the "Deming Cycle".


The plan phase is responsible for planning, do phase is for action, check phase is for monitoring and act phase is for improving purpose in this four phase cycle.


Hence the user can confirm whether the solution has met the desired goal in the Check phase.