Math, asked by brandonloyaltylopez7, 5 months ago

Instruction: Solve the following problems, you can type and upload working or write on foldersheets and upload pictures.

Attachments:

Answers

Answered by tyrbylent
1

Answer:

$4,714.94

Step-by-step explanation:

$2.25 × 500 m³ = $1,125

$2.75 × 500 m³ = $1,375

1825 m³ - (500 m³ + 500 m³) = 825 m³

$3.25 × 825 m³ = $2,681.25

$1,125 + $1,375 + $2,681.25 = $5,181.25 ( a hotel was billed for half year )

100% - 9% = 91% = 0.91

$5,181.25 × 0.91 = $4,714.94 ( the amount was paid before July 14 )