………… is the process of selection of path, which each part of the product will follow
(A) Scheduling
(B) Routing
(C) Follow-up
(D) Dispatching
Answers
Answered by
2
Answer:
is the process of selection of path, which each part of the product will follow
(A) Scheduling
(B) Routing
(C) Follow-up
(D) Dispatching
Answer is (B) Routing
Answered by
0
Option B is correct i.e. Routing.
- Routing is the process of selection of path, which each part of the product will follow.
- Routing determines what work is to be done and where and how will it be done.
- Taking from raw material to the finished product, routing decides the path and sequence of operations to be performed on the job from one machine to another.
- Scheduling function determines when an operation is to be performed or when work is to be completed.
- Dispatching is the action, doing, or implementing stage. It comes after routing and scheduling. Dispatching means starting the process of production. It provides the necessary to start the work.
- Follow-up is designed to track the work effort. The aim is to ensure that what is intended and planned is being implemented.