………… is the process of selection of path, which each part of the product will follow
(A) Scheduling
(B) Routing
(C) Follow-up
(D) Dispatching

Answers

Answered by kumarnaitik296
2

Answer:

is the process of selection of path, which each part of the product will follow

(A) Scheduling

(B) Routing

(C) Follow-up

(D) Dispatching

Answer is (B) Routing

Answered by DevendraLal
0

Option B is correct i.e. Routing.

  • Routing is the process of selection of path, which each part of the product will follow.
  • Routing determines what work is to be done and where and how will it be done.
  • Taking from raw material to the finished product, routing decides the path and sequence of operations to be performed on the job from one machine to another.
  • Scheduling function determines when an operation is to be performed or when work is to be completed.
  • Dispatching is the action, doing, or implementing stage. It comes after routing and scheduling. Dispatching means starting the process of production. It provides the necessary to start the work.
  • Follow-up is designed to track the work effort. The aim is to ensure that what is intended and planned is being implemented.