Is there any common equation for this question???
Answer with steps please then I will give you thanks and mark you as brainlieist
Steps needed
Attachments:
Answers
Answered by
2
here is ur answer
Okay, so 16 workers dig 80 meters in 5 days, right.
First, let's think about how much work each worker did:
80 meters/16 workers = 5 meters per worker
Next, it took each worker how long to do this?
5 meters / 5 days = 1 meter per day. A worker can dig one meter per day.
So if you have 24 workers who can dig 1 meter per day, how many days will it take them to dig 72 meters?
72 meters/24 workers = 3 meters per worker
If a worker can dig 1 meter per day, then the project will take 3 meters/1 meter per day = 3 days
please mark as brainlest