Math, asked by siddu7199, 1 year ago

It takes 10 people 5 days to complete a piece of work at a factory when working 2 hours a day. Working at the same pace, how many days will it take 2 people to do the same work, if they are working 5 hours a day?A) 15B) 2C

Answers

Answered by srilu111
26
see the above pic for answer
Attachments:
Answered by TooFree
22

10 people : 5 days : 2 hours a day


The number of people working is inversely proportional to the number of days needed.

⇒ The more people working, the fewer days they need


Find the number of days needed for 1 person to complete the work:

10 ÷ 10 people : 5 x 10 days : 2 hours a day

1 person : 50 days : 2 hours a day


Find the number of days needed for 2 person to complete the work:

1  x 2 person : 50 ÷ 2 days : 2 hours a day

2 people : 25 days : 2 hours a day


The number of hours worked is inversely proportional to the number of days needed.

⇒ The more hours worked in a day, the fewer days they need


Find the number of days needed if they worked 1 hour a day :

2 people : 25 x 2 days : 2 ÷ 2 hours a day

2 people : 50 days : 1 hours a day


Find the number of days needed if they worked 5 hour a day :

2 people : 50 ÷ 5  days : 1 x 5 hours a day

2 people : 10 days : 5 hours a day


Answer: It will take 10 days