It takes 10 road workers 5 days to complete a road repair when working 2 hours a day. Working at the same pace, how many days will it take 2 people working 5 hours a day to finish it?

Answers

Answered by amitnrw
101

Answer:

It takes 10 road workers 5 days to complete a road repair when working 2 hours a day. Working at the same pace,

Then 2 people working 5 hours a day will finish it in 10 days

Step-by-step explanation:

10 Workers 5 days , 2 hrs a day

so total number of hrs required to do work = 10 * 5 * 2 = 100 Hrs

2 People working 5 hr 1 day

= 2 * 5 = 10 hr in a day

Number of days required to finish job = Total Hrs Required/ Hrs worked in 1 day

= 100/10

= 10 Days


rk43forreal: Great!