It takes 120 minutes to weed a garden with 6 gardeners if the same workof the
done in 30 minutes, how many more gardeners are needed?
Nananani as hy hi-ycle to her school every day. Her averag
with 6 gardeners If the same work is to be
Her average speed is 12km/h​

Answers

Answered by Snehaalmale
2

Answer:

24 workers are needed

hope this helps you

please mark as a brainliest

Answered by AneesKakar
0

Answer:

18 more gardeners.

Step-by-step explanation:

As from the question we get that for 6 gardeners it takes 120 minutes to weed a garden. So, each gardener completes the work in 120*6=720 minutes.

So, now to complete the task in 30 minutes we will be needing 720/30=24  gardeners to do the job.

So, 24-6=18 more gardeners are required to weed the garden in 30 minutes.