It takes 4 men 6 hours to repair a road. How long will it take 8 men to do the job if they work at the same rate?
Answers
Let t be the time taken for the 8 men to finish the job.
4 × 6 = 8 × t
24 = 8t
t = 3 hours
Given:
It takes 4 men 6 hours to repair a road.
To Find:
How long will it take 8 men to do the job if they work at the same rate?
Solution:
It is given that 4 men take 6 hours to do a job and we need to find how much time will it take to do the same job by 8 men
Either we can solve it proportionally like the amount of work is same in both cases but the amount of men has doubled so to maintain the proportionality the amount of time will need to be half of what it used to be so it will be 6/2=3 hours.
Or we can solve it by a formula which is very useful in these types of questions
where,
M= No of men
D= No of days
H= No of hours
W= Amount of work
So now putting the values according to the question we get
Hence, it will take 8 men to do the same job in 3 hours.