It takes 4 men 9 hours to do a job. If one of the men leaves after 6 hours, how many hours will the job take to complete in
total?
Answers
Answered by
0
Step-by-step explanation:
If 4 men can do a job in 30 hours how many men would be required for 9 hours to complete the same job?
If 4 men can do a job in 30 hours, it means that the work requires the input of 4*30 = 120 man-hours.
So, if you wish to complete the same work in 9 hours you will need, 120 man-hours/ 9 hours = 13.33 men.
So engage 14 men for the first 8 hours and then have just one man for the last hour.
Answered by
0
4 men=9 hrs
after completion of 6 hrs 1 man leaves,then;
1 man=9×4
3 mens work=36÷3
=12 hrs-6hrs
=6hrs
answer is 6 hrs.
MARK ME BRAINLIST.