It takes 4 people 2 days to paint a wall. How long would it take if we got 8 people yo do it?

Answers

Answered by prasanthikuchipudi
0

Answer:

1 day

Step-by-step explanation:

we know,

work=men*hours*days

given,

It takes 4 people 2 days to paint a wall.

1 work=4*2

How long would it take if we got 8 people yo do it?

let x be days

1 work=x*8

by equating,

4*2=x*8

x=1 day