It takes 45 days for 20 workers to complete a job. how many days will it take if 30 workers do the same job
Answers
Answered by
0
20 workers takes 45 days to complete a job
1 worker takes (45×20)=900days to complete a job
30 workers takes (900/30)=30 days to complete a same job.
Therefore it takes 30 days to complete same job for 30 workers