It takes 52 days to complete an agreement deal by a certain number of men.After 17 days,300 men are added and 21 days are reduced. How many men were working initially?It takes 52 days to complete an agreement deal by a certain number of men.After 17 days,300 men are added and 21 days are reduced. How many men were working initially?
Answers
Hey Dear,
◆ Answer -
200 men
● Explaination -
Let x be the number of men working initially.
They complete total work in 52 days. So each man will complete 1/52x work per day.
17 days later, 300 men were added reducing time by 21 period. These extra men worked for 52-17-21 = 14 days.
According to this condition -
17 × x × 1/52x + 14 × (x+300) × 1/52x = 1
17/52 + (7x+4200)/52x = 1
(14x+4200)/52x = 1 - 17/52
(14x+4200)/x = 35
35x = 14x + 4200
21x = 4200
x = 200
Therefore, there were 200 men working on the agreement initially.
Thanks dear...
Answer:
300
Step-by-step explanation:
Let original no. of men be N
We are given that It takes 52 days to complete an agreement deal by a certain number of men.
So, Original Job = 52 x N man-days
After 17 days,300 men are added and 21 days are reduced.
Job length = (52-17-21) = 14 days
So, N+300 men are working for 17 days
N men working for 17 days i.e. 17 x N man days
(N+300) men working for 14 days i.e. 14 x (N+300) man days
So, 52N =17N + 14(N+300)
After solving this
21 N = 4200
N= 4200/21
N=200