Math, asked by kaylacapotosti, 1 year ago

It takes 63 minutes for 4 people to paint 9 walls. How many minutes does it take 7 people to paint 4 walls

Answers

Answered by Tamilneyan
0

Answer:

12MINUTES

Step-by-step explanation:

(M1*H1*D1)/W1 = (M2*H2*D2)/W2

MEN1= 3, HOURS1 =63 MIN, WORK1= 9WALLS

MEN2=7 HOURS2 =x MIN WORK2 =4WALLS

(3*63)/9 = (7*X)/4

X=12MIN

Answered by slicergiza
3

Answer:

7 people will take 16 minutes to paint 4 walls

Step-by-step explanation:

Since, when x_1 persons complete a kind of w_1 work in n_1 time and the same kind of w_2 work is completed by x_2 persons in n_2 time,

Then,

\frac{x_1\times n_1}{w_1}=\frac{x_2\times n_2}{w_2}

Here,

x_1=4, n_1 = 63, w_1=9, x_2=7, w_2 = 4

By substituting the values,

\frac{4\times 63}{9}=\frac{7\times n_2}{4}

4\times 252 = 63n_2

\implies n_2=\frac{4\times 252}{63}=4\times 4=16

Hence, 7 people will take 16 minutes to paint 4 walls

#Learn more :

If 63 workers can do a piece of work in 42 days then 27 workers will complete same work in how many day

https://brainly.in/question/3445981

If 5 workers can earn rupees 17500 in 10 days how many workers will earn rupees 29400 in 7 days ?

https://brainly.in/question/4216292

Similar questions