It takes 8 days for 12 men to construct a wall. How many men should be put on the job if it is required to be constructed in 6 days ???
Answers
Answered by
4
Answer:
It's 16 men is required it's just inverse proportion. So did the sum and the answer is 16. Hope this helps you my friend.
Answered by
5
Answer:
HI,
8×12= 6 × x
8×12\6
8×2=16.