It takes 8 days for 12men to built a wall. How many men should be put on the job if it is required
to be constructed in 6 days?
Answers
Answered by
2
Answer:
16
Step-by-step explanation:™
days mens
8 ↔ 12
6 ?
inversely proportional = 8×12/6
= 8×2
= 16 mens
Please mark me brainliest™
Answered by
0
Answer:
Time taken by 12 men to construct a wall = 8 days.
Time taken by 1 man to construct a wall = 12×8 days
∴ Time taken by 6 men to construct a wall =
6
12×8
=16 mens