It takes 8 days for 12men to built a wall. How many men should be put on the job if it is required
to be constructed in 6 days?
Answers
Answered by
2
Answer:
9
Step-by-step explanation:
8days equal to 12 men. 6days equal to 9men
Answered by
50
Answer (^-^)
The concept to be used here is work done = No. of days × No. of mens
Let the number of men required = x
Now since the amount of work done in the both case
8×12 = 6*x
X= 72/6
× = 12 men
So, answer is , it requires 12 men to complete same work is 6 days
Hope it helped.
Let me know if any doubts