Math, asked by ashaj9689, 8 months ago

. It takes 8 people working at equal rates to finish a

work in 96 days. How long will 6 workers take for the

same work?

Answers

Answered by lohita49
0

Answer:

it will take 128 days

Step-by-step explanation:

hope this helps you