Math, asked by ashaj9689, 6 months ago

. It takes 8 people working at equal rates to finish a

work in 96 days. How long will 6 workers take for the

same work,



Plz explain stepwise

Answers

Answered by tonystarkironman94
0

Answer:

since 8 people do work in =96day

1 people do work in days =96/8=12

6people do same work in days =12×6

=72days