It took 1200 carpenter 12 years to build to the temple the king how many rich carpenter complete in 4 years ( do in running mode) ?
Answers
Answered by
0
Step-by-step explanation:
1200× 12 = carpenter × 4
Carpenter = 14400/4
Carpenter = 3600
Answered by
0
Answer:
more the carpenter,less the days.
it shows the relation of inverse Proportion,so
let the required no of carpenters be x,then
1200×12=4×x
or,x=3600