it took 15 days for 30 laboureses to dig a pond. In how many days 25 laboureses could have conpteled the said work
Answers
Answered by
1
Step-by-step explanation:
this is your answer please mark me brainlist
Attachments:
Answered by
0
Step-by-step explanation:
Days Labourers
15 30
X 25
By cross multiplication
15 x 25 = 30 x X
So, X = 15 x 25 /30
X = 12.5
So, 25 labourers would take 12.5 days to complete the said work.