Math, asked by ishwarthakur01, 7 months ago

It took 72 men working 8 hours a day to construct a
wall 250 yard long. 24 feet high and 6 feet wide.
How many men should be engaged to fulfil a
contract for constructing a wall 275 yard long.
25 feet high and 9 feet wide ? If they are to work
9 hours a day and finish the work in the same time
as the past​

Answers

Answered by subhamrout2019
1

Answer:

Step-by-step explanation:

(p1×t1)÷(work1)=(p2×t2)÷(work2)

(72×8)÷(250×24×6)= (p2×9)÷(275×25×9)

P2= 110 men